18–1INTRODUCTION
TheConstructionProcess
Theseveralorganizationalandmanagementmethodsbywhichconstructionmaybe
accomplishedweredescribedinChapter1.Constructionbyageneralcontractoremployed
underaprimeconstructioncontractisonlyoneofthesemethods.However,sincethis
methodofobtainingconstructionservicesiswidelyused,itwillformthebasisforthis
chapter’sdiscussionofcontractconstruction,includingbiddingandcontractaward,con-
structioncontracts,plansandspecifications,andcontractadministration.
ConstructionContractLaw
Constructionprofessionalsarenotusuallylawyersandthereforeshouldnotattempttoactastheir
ownlawyers.However,constructionprofessionalsmusthaveathoroughunderstandingofthe
customarypracticesandunderlyinglegalprinciplesinvolvingcontractconstruction.Virtually
everyactiontakenbyacontractor,constructionmanager,orarchitect/engineerataconstruction
sitehaslegalimplications.Thereissimplynottimetoconsultalawyereverytimeadecisionmust
bemade.Thusconstructionprofessionalsmustunderstandthecontractualconsequencesoftheir
activitiesandbeabletorecognizewhenlegaladviceshouldbesecured.Hencethepurposeofthe
discussionofcontractlawinthischapteristofamiliarizethereaderwiththegeneralprinciplesof
constructioncontractlawandpracticeandtoprovideabasisforfurtherstudy.Astudyofthe
summariesofcourtdecisionspertainingtoconstructioncontractdisputesfoundinmanyprofes-
sionalmagazineswillalsobeveryhelpfulinacquiringfurtherknowledgeinthisarea.
18–2BIDDINGANDCONTRACTAWARD
BidPreparation
IntheUnitedStates,asinmuchoftheworld,constructioncontractingisahighlycompetitive
business.Toprosperandgrow,aconstructioncompanymustachieveareputationforquality
505
506
CHAPTER18
workmanshipandtimelycompletionwhileachievingareasonablereturnonitscapital
investment.Thusprofitisanobviousandprincipalmotiveforbiddingonaconstruction
contract.However,thereareanumberofotherreasonswhyacontractormaychoosetobidon
aproject.Duringtimesoflowconstructionactivity,contractorsmaysubmitbidswithlittleor
noprofitmargininordertokeeptheirequipmentinoperationandpreventthelossofskilled
workersandmanagers.Althoughsuchapolicymaybesuccessfulonashort-termbasis,itis
apparentthatitwillleadtofinancialdisasteriflongcontinued.Otherreasonsforbiddingona
projectincludeadesireforprestigeandthemaintenanceofgoodwillwithregularclients.
Projectsthatreceivewidepublicitybecauseoftheirnationalimportanceortheirunusualnature
areoftenbidatlowprofitmarginsfortheprestigetheyconferonthebuilder.Inthesecases,
thelossofpotentialprofitcanbejustifiedbythepublicrecognitiongained.Likewise,con-
tractorssometimesbidonrelativelyundesirableprojectsinordertomaintainarelationship
withanowner.Insuchcases,theprofitmarginusedforthebidwouldbeexpectedtobehigh.
Regardlessofmotivation,acontractorwhohasdecidedtobidonaprojectmustthenpre-
pareadetailedcostestimatefortheexecutionoftheproject.Thefirststepinpreparationofa
costestimateistotakeoff(orextract)thequantitiesofmaterialrequiredbytheplansandspec-
ifications.Thesequantitiesarethenextended(ormultipliedbyunitcostestimates)toprovide
atotalestimatedmaterialcostfortheproject.Similarestimatesaremadeforlabor,equipment,
andsubcontractcosts.Thecostsofequipment,labor,andmaterialareoftenreferredtoas
direct
costs.
Next,estimatesaremadeoftheadministrativeandmanagementexpensesthatwillbe
incurredattheprojectsite.Thesecostsareoftenreferredtoasjoboverheador
indirectcosts.
Afterallprojectcostshavebeenestimated,itisnecessarytoaddanadditionalamount
(ormarkup)forgeneraloverheadandprofit.
Generaloverhead
mustcoverthecostofallcom-
panyactivitiesnotdirectlyassociatedwithindividualconstructionprojects.Majoritemsof
generaloverheadincludesalariesofheadquarterspersonnel(companyofficials,estimators,
clerks,accountants,etc.),rentandutilities,advertising,insurance,officesupplies,andinter-
estonborrowedcapital.Theusualprocedureforproratinggeneraloverheadexpensestoproj-
ectsistoestimatetotalannualoverheadexpense,dividebytheexpecteddollarvolumeof
constructionworkfortheyear,andthenmultiplybytheprojectbidprice.Theamounttobe
addedfor
profits
is,ofcourse,amanagementdecision.Althoughsomeprojectsmaybebid
withlowprofitmarginsforthereasonsdiscussedearlierinthissection,inthelongrun,con-
structionoperationsmustyieldareasonablereturnoninvestedcapital.Unlessthereturnon
capitalisgreaterthantheyieldofstandardcommercialinvestments,theownerwouldbebet-
teroffinvestinginsuchitemsthaninoperatingaconstructionbusiness.
Biddingstrategy,ortheselectionofaspecificbidpriceforafixed-priceconstruction
contract,isamixtureofartandsciencethatisbeyondthescopeofthisbook.Methodsused
rangefromstatisticalanalysesandapplicationofgametheorytoseat-of-the-pantsdeci-
sions.Thebidpriceactuallysubmittedbyacontractorisusuallybasedonananalysisof
theexpectedcompetitionandthestateoftheconstructionmarketinadditiontothecon-
tractor’sestimateofthecosttoexecutethatproject.
BiddingProcedure
Theprincipalstepsinthebiddingprocedureforafixed-priceconstructioncontractinclude
solicitation,bidpreparation,bidsubmission,bidopening,selectionofthelowestqualified
bid,andcontractaward.Solicitationmayrangefromaninvitationsenttoaselectedfew
507
CONTRACTCONSTRUCTION
contractorstopublicadvertisement.Exceptinspecialcircumstances,U.S.governmental
agenciesarerequiredtosolicitbidsbypublicadvertising.Toensureadequatecompetition,
atleastthreebidsshouldbeobtained.
Contractorsindicatinganinterestinbiddingshouldbesuppliedwithatleastone
completesetofcontractdocuments.Adepositmayberequiredtoensurethereturnof
projectplansandspecificationsfurnishedtounsuccessfulbidders.Thetimeallowedforbid
preparationshouldbebasedonthesizeandcomplexityoftheproject.Threeweekshas
beensuggestedasareasonableminimumtime.
TheAssociatedGeneralContractorsofAmerica,incooperationwithotherprofes-
sionalorganizations,hasdevelopedrecommendedbiddingproceduresforbothbuilding
constructionandengineeredconstructionwhicharedesignedtoensurefairnesstoboth
contractorsandowners(references6and8).Amongtheserecommendationsaretheuseof
standardbidproposalforms,specifyingtheorderofselectionofalternates,andsuggested
minimumtimestobeallowedforbidpreparation.Alternatesareoptionalitemsbeyondthe
basicprojectscope.Sincealternatesmayormaynotbeselectedbytheowner,theirorder
ofselectionwillaffectthedeterminationofthelowestbidprice.
Bidopeningsarefrequentlyopentothepublic,andinsuchcasesbidpricesare
announcedasthebidsareopened.Tofacilitatecommunicationsbetweencontractorsand
subcontractorsimmediatelypriortobidsubmission,thedeadlineforsubmissionofbids
shouldnotoccuronaholidayorthedayimmediatelyfollowingaholiday.
ContractAward
Afterthebidsareopened,theyareevaluatedbytheownertodeterminethelowestqualified
bid.The
qualification
ofacontractoristhedeterminationthatthecontractorpossessesboththe
technicalandfinancialabilitytoperformtheworkrequiredbythecontract.Themethodof
qualificationusedwilldependontheownerinvolved.U.S.governmentregulationsrequirethe
contractingofficer
(personempoweredtoexecutecontractsbindingthegovernment)tomake
aformalfindingthatacontractorisqualifiedtoperformbeforeacontractmaybeawarded.
Anothermethodofbidderqualificationiscalled
prequalification.
Underthisproce-
dureonlythosecontractorsdeterminedtobecapableofperformingareinvitedtosubmit
bidsfortheproject.Amorecommon,althoughindirect,methodofprequalificationisto
requirebondingofthecontractor.Bondsusedinconstructionincludebidbonds,perform-
ancebonds,andpaymentbonds.A
bidbond
guaranteesthatacontractorwillprovidethe
requiredperformanceandpaymentbondsifawardedthecontract.A
performancebond
guaranteescompletionoftheprojectasdescribedinthecontractdocuments.A
payment
bond
guaranteesthepaymentofsubcontractors,laborers,andsuppliersbythecontractor.
Afteridentifyingofthelowestresponsible(i.e.,onefromaqualifiedbidder)andrespon-
sive(i.e.,complyingwithbidrequirements)bid,thewinningbidderisnotifiedbyaletter
ofacceptanceornoticeofaward.Thisdocumentbringsintoforcetheactualconstruction
contractbetweentheownerandthecontractor.
Subcontracts
Subcontracts
arecontractsbetweenaprimecontractorandsecondarycontractorsor
suppliers.Subcontractsarewidelyusedinbuildingconstructionfortheinstallationof
electrical,plumbing,andheatingandventilatingsystems.Thecontractualarrangements
508
CHAPTER18
betweentheprimecontractorandthesubcontractorsaresimilartothosebetweentheowner
andtheprimecontractor.However,subcontractorsareresponsibleonlytotheprime
contractor(nottotheowner)intheperformanceoftheirsubcontracts.Subcontractsare
includedinthissectiononlyforthepurposeofrelatingthemtothebiddingprocess.
Sincesubcontractcostsoftenmakeupamajorportionofthecostforaproject,itis
essentialthattheprimecontractorobtaintimelyandcompetitivepricesforsubcontract
services.Infairness,thesuccessfulprimecontractorshouldexecutecontractswiththose
subcontractorswhosepriceshavebeenusedforpreparationofthebid.However,afterre-
ceivingthecontractaward,somecontractorsattempttoobtainlowersubcontractpricesby
negotiatingwithothersubcontractors.Thispracticeisreferredtoas
bidshopping
andis
widelyconsideredanunethicalpracticewhichleadstopoorsubcontractorperformance.As
aresult,biddingproceduresoftenrequirethebiddertoidentifysubcontractorsatthetime
ofbiddingandtouseonlythesesubcontractorsontheproject.Somegovernmentalagen-
ciesevengosofarastoawardseparateprimecontractsforgeneralconstructionandfor
eachareaofspecialtywork.Whileprotectingthesubcontractors,suchaproceduregreatly
complicatesprojectcontrolandcoordination.
18–3CONSTRUCTIONCONTRACTS
ContractElements
Thelegallyessentialelementsofaconstructioncontractincludeanoffer,anacceptance,
andaconsideration(paymentforservicestobeprovided).Theofferisnormallyabidor
proposalsubmittedbyacontractortobuildacertainfacilityaccordingtotheplans,speci-
fications,andconditionssetforthbytheowner.Acceptancetakestheformofanoticeof
award,asstatedearlier.Considerationusuallytakestheformofcashpayment,butitmay
legallybeanythingofvalue.
ContractTypes
Contractsmaybeclassifiedinseveralways.Twoprincipalmethodsofclassificationareby
methodofawardandbymethodofpricing.Thetypesofcontractby
methodofaward
arefor-
mallyadvertisedcontractsandnegotiatedcontracts.Theprocedureforthesolicitationand
awardofanadvertisedconstructioncontractwasdescribedintheprevioussection. A
negotiatedcontract
,asthenameimplies,isonenegotiatedbetweenanownerandacon-
structionfirm.Alltermsandconditionsofthefinalcontractarethosemutuallyagreedtoby
thetwoparties.Whilefederalprocurementregulationsestablishformallyadvertisedcompet-
itivebiddingasthenormalprocess,negotiatedcontractsarepermittedunderspecialcircum-
stances.Privateownersmay,ofcourse,awardacontractinwhatevermannertheychoose.
Thetwotypesofcontractbymethodofpricingare
fixed-pricecontracts
and
cost-type
contracts.
Eachofthesetypeshasanumberofvariations.Therearetwoprincipalformsof
fixed-pricecontracts:firmfixed-pricecontractsandfixedpricewithescalationcontracts.
Otherclassificationsoffixed-pricecontractsinclude
lump-sumcontracts
and
unit-price
contracts.
A
lump-sumcontract
providesaspecifiedpaymentforcompletionofthework
describedinthecontractdocuments.Unit-pricecontractsspecifytheamounttobepaidfor
509
CONTRACTCONSTRUCTION
eachunitofworkbutnotthetotalcontractamount.Suchcontractsareusedwhenthe
quantitiesofworkcannotbeaccuratelyestimatedinadvance.Theprincipaldisadvantages
ofunit-pricecontractsaretherequirementforaccuratelymeasuringtheworkactuallyper-
formedandthefactthattheprecisecontractcostisnotknownuntiltheprojectiscompleted.
Acombinationoflump-sumandunit-priceprovisionsmaybeusedinasinglecontract.
Fixedpricewithescalationcontractscontainaprovisionwherebythecontractvalue
isadjustedaccordingtoaspecifiedpriceindex.Suchcontractsreducetherisktothecon-
tractorduringperiodsofrapidinflation.Sincethealternativeduringperiodsofinflationis
forthecontractortoaddalargecontingencyamountforprotection,theuseofanescalation
clausemaywellresultinalowercosttotheownerthanwouldafirmfixed-pricecontract.
Inspiteofthis,fixed-priceconstructioncontractswithescalationclauseshavenotbeen
widelyusedintheUnitedStates.
Cost-type(orcost-plus)contractsareavailableinanumberofforms.Someofthese
include:
•Costpluspercentageofcost.
•Costplusfixedfee.
•Costplusfixedfeewithguaranteedmaximumcost.
•Costplusincentivefee.
A
costplusapercentageofcostcontract
paysthecontractorafeethatisapercentageofthe
project’sactualcost.ThistypeofcontractmaynotbeusedbyU.S.governmentagenciesbe-
causeitprovidesanegativeincentiveforthecontractortoreduceprojectcost.Thatis,the
highertheprojectcost,thegreaterthecontractor’sfee.Themostwidelyusedformofcost
reimbursementcontract,the
costplusfixedfeecontract
,doesnotrewardthecontractorfor
anincreasedprojectcostbutstillfailstoprovideanyincentivetominimizecost.The
cost
plusfixedfeewithguaranteedmaximumcostcontract
addssomeoftheriskofafixed-price
contracttothecostreimbursementcontractbecausethecontractorguaranteesthatthetotal
contractpricewillnotexceedthespecifiedamount.Henceitistobeexpectedthatthecon-
tractor’sfeeforthistypeofcontractwillbeincreasedtocompensatefortheaddedriskin-
volved.The
costplusincentivefeecontract
isdesignedtoprovideanincentiveforreducing
projectcost.Inthistypeofcontract,thecontractor’snominalortargetfeeisadjustedupward
ordownwardinaspecifiedmanneraccordingtothefinalprojectcost.Thusthecontractor
isrewardedbyanincreasedfeeifabletocompletetheprojectatacostlowerthantheorig-
inalestimate.Allcost-typecontractsshouldclearlydefinetheitemsofcostforwhichthe
contractorwillbereimbursedandspecifythebasisfordeterminingtheacceptabilityofcosts.
ContractDocuments
Aconstructioncontractconsistsofthefollowingdocuments:
•Agreement.
•ConditionsoftheContract(usuallyGeneralConditionsandSpecialConditions).
•Plans.
•Specifications.
Plik z chomika:
Januszek66
Inne pliki z tego folderu:
Back Seat_ A Mumbai Tale - Aditya Kripalani.mobi
(755 KB)
Brief Wondrous Life of Oscar Wao, The - Junot Diaz.opf
(3 KB)
Don't Make Me Think, Revisited_ - Steve Krug.mobi
(9256 KB)
M. T. Anderson - Norumbegan 03 - The Empire of Gut and Bone # (v5.0).epub
(2209 KB)
M. T. Anderson - Norumbegan 02 - The Suburb Beyond the Stars # (v5.0).epub
(2105 KB)
Inne foldery tego chomika:
Dokumenty
Galeria
LUDLUM ROBERT
Midi - Kar
Mszał Rzymski PL
Zgłoś jeśli
naruszono regulamin